11/01/2023 - Cullompton High Street Heritage Action Zone - Higher Bullring Public Realm Enhancement Project

RESOLVED

 

(a) that the public realm enhancement design (developed as part of the High Street Heritage Action Zone project) for the Higher Bullring area of Cullompton, as set out in Appendix 1, at a cost of £828,016, to proceed to tender and construction be approved, noting there is no cost to Devon County Council;

 

(b) that the Director of Climate Change, Environment and Transport, in consultation with the Local Member and Cabinet Member for Climate Change, Environment and Transport be given delegated authority to make minor amendments to the scheme design; and

 

(c) that an increase to the 2022/23 capital programme by £96,711, funded by developer contributions, be approved.