Agenda item

Report of the Director of Finance and Public Value (Code), presenting the outturn for 2024/2025, attached.

Decision:

RESOLVED

 

(a) that the draft outturn for 2024/25, after carry forwards and contributions to and from balances, reserves and provisions, shows a balanced break even position for the General Fund Balance, against the approved revenue budget;

 

(b) that the 2024/25 revenue outturn be approved, including transactions on earmarked reserves and provisions, spending against budget, treatment of over and under spending and the implications for balances, as set out in the tables and the narrative of the report;

 

(c) that the 2024/25 capital outturn is approved including spending against budget and proposed carry forwards, in accordance with the tables;

 

(d) that the addition to the 2025/26 capital programme as set out in section 12 in relation to Okehampton Interchange be approved;

 

(e) that the use of capital finance as set out in the Determination of Capital Finance section 11 of the report also be approved;

 

(f) that a total of £16.1 million be set aside from revenue resources as Minimum Revenue Provision for the repayment of capital borrowing;

 

(g) that the Prudential Indicators as set out in section 10 of the report be noted; and

 

(h) that the total monies owing to the Council as at 31st March 2025 also be noted.

 

Minutes:

The Cabinet considered the Report of the Director of Finance and Public Value (DPF/25/52), which presented the outturn for 2024/2025.

 

In summary, the Authority had performed well financially and had achieved a balanced outturn position, despite the ongoing challenge to meet the cost and complexity of needs of demand-led people services in the care sector.

 

The budget had been set with a need to deliver significant savings and an extensive amount of work had been undertaken by strategic and directorate leadership teams to deliver planned savings. Whilst good progress had been made it had not always been possible to deliver to plan, however, Directorates had identified alternative measures to mitigate this to some degree.

 

The table at 1.3 summarised savings delivery across the authority by directorate, with savings of £40.2 million achieved against budgeted delivery of £49.6 million.

 

A key priority continued to be tackling the increasing deficit position relating to Special Educational Needs and Disabilities (SEND). The DSG SEND Deficit continued to be accounted for separately to the General Fund reserve balance under statutory regulations. The Council had continued to participate in the Department for Education (DfE) Safety Valve Programme, aimed at improving performance and reducing the cumulative deficit. The 2024/25 DSG SEND overspend transferred to the accumulated deficit was £51.4 million, increasing the accumulated deficit to £169.1 million.

 

There was a balanced break even position for the General Fund Balance in 2024/25 on a net Budget of £637.5 million.

 

In addition, there had been a significant impact from applying the flexible use of capital receipts (FUCR) policy agreed by Council, which enabled capitalisation of £6.5 million of revenue costs related to service transformation and improvement.

 

The underspend position at the end of the year was £3.2 million which had  enabled the Authority to fund an increase in the provision for non-recovery of income (bad debt) by £1 million, increase the insurance provision by £1 million, carry forward £1 million to support vulnerable families, and carry forward £195,000 for Local Government Reorganisation.

 

The General Fund balance had been maintained at £16 million. The balance of total earmarked reserves as at 31st  March 2025, excluding schools and non-schools carry forwards, was £121 million.

 

Within services there were overspends reported primarily to the budgets for Integrated Adult Social Care and to Children and Young People's Futures, for which section 2 of the report provided further detail, along with the detailed final financial position of all service areas.

 

In summary, Children and Young People's Futures was an overspend of £5.5 million excluding the Dedicated Schools Grant (DSG). Public Health and Communities had delivered an underspend of £2.4 million, after considering carry forward requests. The outturn position for the Performance and Partnerships Directorate was an underspend of £1.2 million. Corporate Services showed an overall overspend of £348,000 after taking into account the carry forward of grants and contributions. The overall position for Climate Change, Environment and Transport, after carry-forward requests, was an underspend of £1.9 million.

 

Investment in road infrastructure also remained a pressure with spend on highways safety defects (‘potholes’) showing a £2.2 million overspend against budget due to a significant increase in potholes throughout the year. The overall pressure on the Highways Maintenance budget had been further increased by the significant number of storms encountered throughout the year and the prolonged icy conditions from November to early March. 

 

The report further proposed an addition to the 2025/26 capital programme relating to the Okehampton Interchange. In addition to the carry forwards referred to in section 7 and table 2, this report sought to increase the capital programme by £3,286,897 in 2025/26 in respect of the Okehampton Interchange project, to be funded from S106 contributions that had been received. The project had an approved total budget of £14.95 million, of which £3.8 million had been incurred as at March 2025.

 

The enabling works for the station had commenced in Autumn 2024 while detailed design continued on the main contract over the Winter and Spring. Subject to finances being in place, the main works Implementation Agreement between Devon County Council and Network Rail were planned for sign off in early July 2025. The footbridge and lift shaft were planned for installation in the Autumn and station completion planned in Spring/early Summer.

 

The matter having been debated and the other relevant factors set out in the Director’s Report having been considered:

 

it was MOVED by Councillor Buczkowski, SECONDED by Councillor Brazil, and

 

RESOLVED

 

(a) that the draft outturn for 2024/25, after carry forwards and contributions to and from balances, reserves and provisions, shows a balanced break even position for the General Fund Balance, against the approved revenue budget;

 

(b) that the 2024/25 revenue outturn be approved, including transactions on earmarked reserves and provisions, spending against budget, treatment of over and under spending and the implications for balances, as set out in the tables and the narrative of the report;

 

(c) that the 2024/25 capital outturn is approved including spending against budget and proposed carry forwards, in accordance with the tables;

 

(d) that the addition to the 2025/26 capital programme as set out in section 12 in relation to Okehampton Interchange be approved;

 

(e) that the use of capital finance as set out in the Determination of Capital Finance section 11 of the report also be approved;

 

(f) that a total of £16.1 million be set aside from revenue resources as Minimum Revenue Provision for the repayment of capital borrowing;

 

(g) that the Prudential Indicators as set out in section 10 of the report be noted; and

 

(h) that the total monies owing to the Council as at 31st March 2025 also be noted.

Supporting documents: