Network Rail presentation on developments.
Minutes:
(a) Phase 1: Dawlish, Marine Parade
· Lighting had now been commissioned, following favourable feedback from stakeholders;
· The remaining works were lifting eye remedial works and minor snagging.
(b) Phase 2: Dawlish Sea Wall, Coastguards to Colonnade
The high level programme was presented for all the works which were due for completion during 2023;
(c) Phase 3: Parsons Tunnel North Portal Resillience
This was due for completion at the end of September 2022;
(d) Phase 4: Dawlish to Holcombe Earthwork Resillience
(e) Phase 5: Parsons Tunnel to Teignmouth
Members’ questions/comments, together with responses (in brackets) included:-
- that the progress to date was welcome (including the phase 2 proposed lighting);
- however an issue that needed urgent attention related to pollution affecting the beach/sea due to the deterioration of Marine Parade/phase 1 joint material. (Network Rail advised the neoprene joint material infilled the gaps between the panels to enable the concrete to be infilled behind. A lack of joint material allowed pebbles to get into the joints. Network Rail had been working with the designers regarding required remediation. Whilst this had no impact on the structural integrity of the wall, the materials and pollution issues would be addressed as soon as possible);
- further consideration had been sought regarding the location and operation times of generators, to minimise the pollution impact on the local community at Dawlish for Phase 2 and the potential for similar issues for the Parsons Tunnel Phase 3 compound. (Network Rail confirmed that a request for mains power had been made for the Phase 2 compound. Whilst agreements were being progressed the generators would be changed to use hydrotreated vegetable oil (HVO) instead of conventional fossil fuel. A further response would be provided to members in relation to proposals to mitigate compound pollution at Parsons Tunnel phase 3);
- a request had been made to include cycle route within the scheme between Smuggler’s Lane and Teignmouth, to link into the existing route (Network Rail advised this had formed part of discussions between Network Rail, Devon County Council and SUSTRANS. This would be reviewed once the geotechnical design review had been carried out and the potential change to the overall scheme was understood);
- a request had been made that breakwaters were considered as part of Phase 5 (off-shore/perpendicular to beach, e.g. to help to encourage more beach/reduce erosion). (This would be passed onto the Network Rail’s re-evaluation team for consideration);
- whether Network Rail had been impacted by the current ongoing supply issues of some building materials (Network Rail advised that minor modifications/ alterations had been made to help with some material supply issues, together with the use of a number of different precast concrete suppliers where the Covid-19 pandemic had impacted on available labour);
- -confirmation sought from Network Rail on the timescale regarding whether the sea lavender translocation would be successful at Parsons Tunnel North Portal (Phase 3) and the proposed plan if this did not take root (advice would be sought and a response made after the meeting).
RESOLVED: that Network Rail be thanked for their presentation, noting that an update/response would be provided on the Member issues raised above, as appropriate (where available see post meeting note at * above).