316 Proposed Long Lane widening and a new link road on Silverdown Office Park, near Exeter Airport, Broadclyst pdf icon PDF 511 KB

Report of the Head of Planning Transportation and Environment (PTE/19/13) on the Proposed Long Lane widening and new link road on Silverdown Office Park (near Exeter Airport, Broadclyst), attached. 

 

An Impact Assessment is attached for the attention of Members at this meeting.     

 

 

Additional documents:

Minutes:

(Councillors Way and Whitton attended in accordance with Standing Order 25(2) and spoke to this item).

 

The Cabinet considered the Report of the Head of Planning, Transportation and Environment (PTE/19/13) seeking approval to proceed with the construction of widening on Long Lane and a new link road on Silverdown Office Park (near Exeter Airport, Broadclyst), the Report being circulated prior to the meeting in accordance with regulation 7(4) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.

 

The Report highlighted that in relation to the widening of Long Lane (near the Airport), the section extended from the Airport Terminal entrance, past the hangers and the FlyBe Academy/Hampton by the Hilton hotel through to Harrier Court in the East, a length of approximately 1.25 km.  It was proposed to widen to a 6.5m width to provide sufficient access to develop the employment Enterprise Zone area known as Airpark. To facilitate the works, a diversion route would be required for traffic at the site which meant the construction of a section of road to connect Silverdown Office Park to the FlyBe Academy access road, known as the “Silverdown Link”.  Design and scheme works would be funded by the Enterprise Zone, supported by private contributions.

 

The scheme presented to Cabinet comprised four main sections:

 

·         Long Lane: Airport Terminal entrance, to Car Park 1;

·         Long Lane: Car Park 1 to Training Academy/Hotel;

·         Long Lane: Training Academy/Hotel to Harrier Court; and

·         Silverdown link.

 

The proposals for the four sections identified above were shown on drawing B23006BZ-01-017 included as an Appendix to the Report.

 

The scheme provided benefits to the area, ensuring that access could be maintained to key businesses and to facilitate growth at the Airpark site and the delivery of the France-AlderneyBritain (FAB) connector.

 

In order to ensure that the scheme had as wide support as possible, six meetings had been held with partners and stakeholders, as well as representatives of Airpark (e.g. Airport, Flybe, Airport Hotel, FAB project, Highways England and main landowners).

 

The scheme was estimated to cost £3 millions, to be constructed over two financial years 2019/20 & 2020/21. The Enterprise Zone Board had approval to borrow the funds (as part of a wider package of support within the Enterprise Zone) and additional approval was being sought from East Devon District Council’s Cabinet (6 March 2019).  There was currently no cost to the County Council to construct the scheme; however it would be expected to manage any cost overruns and recover these from East Devon District Council.

 

Construction would not commence until all funding and legal agreements were in place, including confirmation and sign up from landowners.

 

The Cabinet noted the financial risks to the Council (as well as East Devon District Council) should the scheme not proceed with the reduced ability to generate the anticipated business rates from the Airpark Development and also the other the risks identified which included the scheme programme and costs, the funding package, progression of the FAB project  ...  view the full minutes text for item 316