Skip to content

Decision details

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Decision:

RESOLVED

 

(a) that the preferred scheme, as shown in Appendix 1, to proceed to tender and construction at an estimated cost of £1,234,376 be approved; and

 

(b) that the Director of Climate Change, Environment and Transport be given delegated powers, in consultation with the Cabinet Member for Highway Management and the local Member, to make minor amendments to the scheme details.

Reason Key: Strategic, Political or Financial Significance;

Divisions Affected: Seaton & Colyton;

Other reasons / organisations consulted

Public consultation for whole route in 2011

Consultees

Local Member, Cabinet Member, landowners

Contact: Meg Booth, Director of Climate Change, Environment and Transport Email: meg.booth@devon.gov.uk.

Report author: Meg Booth

Publication date: 08/03/2023

Date of decision: 08/03/2023

Decided at meeting: 08/03/2023 - Cabinet

Accompanying Documents:


Top