RESOLVED
(a) that the advertising of the traffic regulation orders necessary for the
schemes in the Report be approved and to make and seal the orders subject
to the requirements of the legislation and the council’s procedures;
(b) that subject to the resolution of the traffic regulation orders, the
construction of the Exeter Central Corridor scheme, as shown in Appendix 1,
be approved, at an estimated cost of £1,022,000;
(c) that subject to the resolution of the traffic regulation orders, the
construction of the Exeter Eastern Corridor scheme, as shown in Appendix 2,
be approved, at an estimated cost of £564,000;
(d) that subject to the resolution of the traffic regulation orders and the funding
sources being confirmed, that the construction of the Braunton Road,
Barnstaple scheme, as shown in Appendix 3, be approved, at an estimated
cost of £939,000;
(e) that the construction of the Newton Abbot scheme, as shown in Appendix
4, be approved, at an estimated cost of £245,000;
(f) that delegated authority is given to the Director of Climate Change,
Environment and Transport in consultation with the Cabinet Member for
Highway Management, the Cabinet Member for Climate Change,
Environment and Transport and the relevant Local Members to approve minor
changes to the schemes.