10/07/2024 - Bus Service Improvement Plan Tranche 2 Schemes

RESOLVED

 

(a) that the advertising of the traffic regulation orders necessary for the

schemes in the Report be approved and to make and seal the orders subject

to the requirements of the legislation and the council’s procedures;

 

(b) that subject to the resolution of the traffic regulation orders, the

construction of the Exeter Central Corridor scheme, as shown in Appendix 1,

be approved, at an estimated cost of £1,022,000;

 

(c) that subject to the resolution of the traffic regulation orders, the

construction of the Exeter Eastern Corridor scheme, as shown in Appendix 2,

be approved, at an estimated cost of £564,000;

 

(d) that subject to the resolution of the traffic regulation orders and the funding

sources being confirmed, that the construction of the Braunton Road,

Barnstaple scheme, as shown in Appendix 3, be approved, at an estimated

cost of £939,000;

 

(e) that the construction of the Newton Abbot scheme, as shown in Appendix

4, be approved, at an estimated cost of £245,000;

 

(f) that delegated authority is given to the Director of Climate Change,

Environment and Transport in consultation with the Cabinet Member for

Highway Management, the Cabinet Member for Climate Change,

Environment and Transport and the relevant Local Members to approve minor

changes to the schemes.