Issue - decisions

12/10/2023 - Bus Service Improvement Plan: Tranche 1 Capital Schemes

RESOLVED

 

(a) that theadvertising of the traffic regulation orders necessary for the schemes in this report and to make and seal the orders subject to the requirements of the legislation and the council’s procedures, be approved;

 

(b) that subject to the resolution of the traffic regulation orders, the construction of the bus lane scheme in Roundswell, as shown in Appendix 1, at an estimated cost of £525,000 be approved;

 

(c) that subject to the resolution of the traffic regulation orders, the construction of the New North Road Bus Gate in Exeter City Centre, as shown in Appendix 2, at an estimated cost of £400,000, be approved; and

 

(d) that the Director of Climate Change, Environment and Transport be given delegated authority, in consultation with the Cabinet Member for Highway Management, the Cabinet Member for Climate Change, Environment and Transport and the relevant Local Members, to approve minor changes to the schemes.