Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
RESOLVED
(a) that approval be given for a scheme in Dawlish which assists in connecting Elm Grove Road and the A379 Exeter Road, and includes provision of a bridge with embankments, sustainable urban drainage together with cycle lanes and footpaths, as identified in the Local Plan, to proceed to tender and construction;
(b) that delegated authority be given to the Director of Climate Change, Environment and Transport, in consultation with the Local Member and Cabinet Member for Climate Change, Environment and Transport, to make minor amendments to the scheme design; and
(c) that an increase to the 2022/23 capital programme by £286,065 and 2023/24 by £5,564,465, funded by external contributions, be approved.
Reason Key: Strategic, Political or Financial Significance;
Divisions Affected: Dawlish;
Other reasons / organisations consulted
Teignbridge District Council (TDC) community
engagement for Development Framework Master Plan, Planning
consultation via TDC, TDC/DCC Member briefing at pre-planning
stage
Consultees
Teignbridge District Council Members, DCC
Member, stakeholders and public
Contact: Meg Booth, Director of Climate Change, Environment and Transport Email: meg.booth@devon.gov.uk.
Report author: Meg Booth
Publication date: 12/10/2022
Date of decision: 12/10/2022
Decided at meeting: 12/10/2022 - Cabinet