Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
RESOLVED
(a) that the following schemes for tender, subject to the resolution of legal and land assembly agreements, and planning consents, be approved;
I.Spine road phase 1a as shown in Appendix 1
II.Spine road phase 1b as shown in Appendix 2
III.Pedestrian/cycle bridge as shown in Appendix 3;
(b) that any necessary Traffic Regulation Orders be advertised, and if no objections received, be made and sealed;
(c) that following receipt of planning consents, land acquisition is commenced by negotiation and approval given to use compulsory purchase powers, if required;
(d) that the Director of Climate Change, Environment and Transport be given delegated authority, in consultation with the Cabinet Member for Highway Management and the Cabinet Member for Climate Change, Environment and Transport to award the construction contract for delivery of the Schemes in Appendix 1, 2 and 3 with a combined cost of £18.908 million; and
(e) that the Director of Climate Change, Environment and Transport be given delegated authority, in consultation with the Cabinet Member for Highway Management, the Cabinet Member for Climate Change, Environment and Transport and the relevant Local Members to make minor amendments to the scheme, as required.
Reason Key: Strategic, Political or Financial Significance;
Divisions Affected: Bickleigh & Wembury;
Other reasons / organisations consulted
Meetings / correspondence and consultation to
be undertaken as part of the planning process for both; existing
public consultation completed on the pedestrian/cycle
bridge
Consultees
Landowners and members of the public
Contact: Meg Booth, Director of Climate Change, Environment and Transport Email: meg.booth@devon.gov.uk.
Report author: Meg Booth
Publication date: 10/04/2024
Date of decision: 10/04/2024
Decided at meeting: 10/04/2024 - Cabinet